Construction update 5/22/17

 

Construction progress – As of the date of this report the following tasks have been completed since the last update

Phase 1:

  • Window installed in Chapel where fire escape door was
  • Wainscoting , trim, and heat registers painted in Chapel
  • Carpet installed in Chapel, landing, and stairs
  • All woodwork and railings around stairs installed and painted
  • Hardwood installed on stage in sanctuary
  • Walkway and closet complete on west side of sanctuary
  • Double doors for new wider opening complete on west side of sanctuary
  • All remaining wainscoting installed and painted in sanctuary
  • Youth area construction started in sanctuary
  • LVT floor installed in meeting hall and copy room
  • Outside windows installed in Sharan’s and Donna’s offices
  • Window looking into meeting hall in Donna’s office installed
  • Carpet installed in Sharan’s and Donna’s offices, also in Nursery

Phase 2:

  • Elevator pit poured
  • East footers and basement walls poured that are adjacent to chapel building
  • All sewer lines run under basement floor
  • Support girders and floor trusses received

 

The open house has been rescheduled for Sunday June 4th from Noon until 2:00 pm for the final reveal of the renovations in the Sanctuary and Chapel building.  There is limited handicapped parking at the end of the Manse driveway.  Otherwise, there will be parking on the street and a few spots outside the gate in the main lot.