Construction update 5/21/2018
As of the date of this report the following tasks have been completed since the last update:
· Level 1 social hall complete except for partial painting in stairwells
· A/C condensers installed for furnaces on west side
· Sprinklers and ceiling in basement complete
· Projected date for Certificate of Occupancy 5/31/18
· Remaining items outside (lawn, parking lot, siding, lighting, etc.) will be completed in June.