Construction update 4/22/2018

 

As of the date of this report the following tasks have been completed since the last update    

  • All four furnaces operational
  • Basement floor painted (needs second coat)
  • Additional underlayment installed on Social hall floor
  • Vinyl floor complete in Social hall
  • Baseboards complete in social hall
  • Closet doors in Social hall installed
  • Water line turned on
  • Bathrooms on main level 90% complete
  • Bathrooms in basement 60% complete
  • Sprinkler system in fabrication, installation starting the week of 4/23
  • Sheet rock finished and ready for painting in stairwells and 3rd level
  • Final stair treads and risers installed and painted in all stairwells (need final coat)