Construction update 3/20/2018

 

Construction progress – As of the date of this report the following tasks have been completed since the last update

  • 3rd level future bathrooms framed, door openings framed wall outside bathrooms finished
  • Stainless countertops in kitchen finished
  • Outside doors near kitchen and northwest stairwell installed
  • New hot water baseboard heat run to 3rd level annex complete
  • New subfloor installed in social hall
  • Rainbow colored accent walls painted in basement class rooms
  • Basement floor painted
  • Gas lines fully installed and operational
  • Two furnaces installed and tested
  • Siding on north side complete (east side still remaining)
  • Baseboard and door molding painted and ready to install.
  • Gutters and downspouts installed
  • Granite sills installed in basement and main level
  • East door (facing manse) installed
  • Bathroom floors tiled