Construction update 2/20/2018
Construction progress – As of the date of this report the following tasks have been completed since the last update
- Walls painted on levels one and two
- Kitchen cabinets installed, counter tops being wrapped with stainless steel
- Kitchen equipment installed
- Stained glass windows in foyer installed
- Cabinets and glass case installed in foyer
- Glass front doors installed
- Glass door on east side installed
- Ceiling, lights, and chandelier installed in foyer
- Elevator installed and operational (pending inspection)
- Railings on ramp installed
- Granite window sills installed on main level
- Roll top doors for kitchen pass through windows complete\
- Framing complete for upstairs future bathrooms