Construction update 2/20/2018

 

Construction progress – As of the date of this report the following tasks have been completed since the last update

  • Walls painted on levels one and two
  • Kitchen cabinets installed, counter tops being wrapped with stainless steel
  • Kitchen equipment installed
  • Stained glass windows in foyer installed
  • Cabinets and glass case installed in foyer
  • Glass front doors installed
  • Glass door on east side installed
  • Ceiling, lights, and chandelier installed in foyer
  • Elevator installed and operational (pending inspection)
  • Railings on ramp installed
  • Granite window sills installed on main level
  • Roll top doors for kitchen pass through windows complete\
  • Framing complete for upstairs future bathrooms