Construction progress – As of the date of this report the following phase-2 tasks have been completed since the last update

  • All drywall is installed in finished areas on level 1 and 2
  • Main level mud/taping complete
  • Kitchen painting complete
  • Siding 75% complete
  • Stained glass windows in foyer installed
  • Elevator installed
  • Doors and jams painted and ready for installation
  • Porch roof over ramp complete
  • Door openings between new/old buildings complete
  • Rough-in plumbing work complete
  • Heating systems and ductwork 90% complete